The works involved cutting 2no. 25mm deep horizontal chases in the newly formed structure and preparing the surface to receive an additional 25mm of cover. Stainless steel mesh was utilised to ensure a permanent solution and Fosroc HB45 concrete repair mortar specified as the overlay materials.
Client
Balfour Beatty
Duration
1 Month
Scope of Works
-
Tower access
-
Preparaton of concrete surfaces using mechanical scabblers
-
Cut 25mm deep termination channel
-
Stainless steel expomat mesh and stainless fixings, drill and fit expomat
-
Application of 2no layers of Fosroc HB45.