The Bedford site houses a state-of-the-art manufacturing plant, but the eight storey 1940's thin walled concrete mill structure required significant refurbishment work as it was suffering from carbonation and chloride contamination. As the site is a busy manufacturing plant it was vital that the remedial works had minimal impact on the running of the factory.
Client
W Jordan Ltd
Duration
1 Year
Scope of works
-
Setting up site compound
-
Internal protection
-
Extensive concrete repairs
-
Cladding
-
Structural steel works
-
Roof work.