Concrete, render and brick repairs to 3 no. 11 storey blocks of flats, each containing 66 residential flats of mixed tenure which were occupied throughout the duration of the works.
Client
Ealing Council
Duration
12 Weeks
Our scope of works
-
Cradle access
-
Cleaning discoloured and stained brickwork
-
Brickwork repairs and repointing
-
Concrete repairs and coatings
-
Render repairs
-
Temporary removal and reinstatement of satellite dishes and pigeon netting.