Prior to starting works onsite we undertook a make safe abseil survey and hammer test to establish the full extent of repairs.
Client
Marriott Hotel
Duration
7 Months
Scope of Works
-
Water jetting
-
Hammer testing
-
Concrete repairs
-
Application of an epoxy primer and render coat to eliminate the glazed tiled finish
-
Application of mastic to all movement joints and window surrounds
-
Application of three coats of Remmers Silicone Paint.