Technical Building TBA was Grade II listed in 1996 and TBE is situated in BA Operations Base and contains offices, workshops and maintenance hangers.
Client
British Airways PLC
Duration
4 Months
Our Scope of Works to TBA & TBE
-
Repair of exposed concrete and brick facades including soffits to match existing concrete.
-
Brick repairs & repointing
-
Insertion of movement joints
-
Remove textured coating
-
Concrete repairs
-
Apply a textured concrete coating system
-
Replacement of window/door sills and heads
Additional Works were then secured to carry out concrete repairs to 8 Counter Weight Ballast Tanks which support the arches to the entrance to the aircraft hangers.
-
MEWPS access
-
Preparation of surfaces
-
Concrete repairs
-
Waterproof render
-
Application of coatings