Gunite have finished another phase of the exterior refurbishment of Birmingham University - Staff House, Edgbaston. Works were over 4 floors and included a two-storey annex housing a bank and shops.
Client
University of Birmingham
Duration
5 Months
Our Scope of Works
-
Water jet cleaning to concrete
-
Hammer testing
-
Patch repairs
-
MEWPS access
-
Fairing coat
-
Anti-carbonation coatings
-
Gutter lining
-
Balcony screed
-
Replacement sealant/window frames
-
General decoration
-
Balcony hand rails
-
Asbestos panels and cladding to roof plant replaced with Trespa Meteon cladding panels.